The Dominican Republic approved a new tender for up to 900 MW of solar photovoltaic and wind power generation with mandatory storage, just weeks after launching a call for 200 MW and 800 MWh of batteries for existing renewable power plants.
The Superintendency of Electricity (SIE) formalized the procedure through Resolution SIE-155-2026-LCE to supply EDENORTE, EDESUR and EDEESTE under 15-year contracts, with a maximum term of 24 months from the signing to start the supply .
The terms stipulate a single contracting block , with individual projects ranging from 2 MW to 300 MW . Furthermore, the power plants must have their own battery energy storage systems (BASS) capable of guaranteeing four hours of discharge throughout the contract period .
It should be clarified that the call identified as EDES-LP-NGR-01-2026 will only admit solar and wind projects that have a valid definitive concession , granted before the start of the prequalification phase.
While battery installations may be operational before or after the competitive bidding process, they must maintain their performance throughout the 180-month supply period and comply with the operational requirements for grid connection.
The scheme thus establishes specific obligations for the participation of BESS systems. These include ramp control, which limits the variation in active power to 25% of the plant's nominal capacity per hour , in order to manage fluctuations in variable renewable generation. Frequency regulation, fast response, and synthetic inertia are also required.
The equipment must incorporate grid forming functionalities, voltage regulation at the point of interconnection and black start capability.
The Dominican Republic adds another call for bids after tendering 200 MW of batteries.
The new contract is added to the country's electricity auction agenda after the SIE published the terms of a procedure for 200 MW of power and 800 MWh of storage in early November, through Resolution SIE-141-2026-LCE .
Unlike the 900 MW call, this process is aimed exclusively at existing solar and wind power plants that have long-term contracts with distributors , with the aim of incorporating batteries into their facilities.
The auction anticipates its award on February 25, 2027 , supply agreements for 15 years and a maximum period of 12 months to implement the equipment and obtain the commercial operation authorization .
Regarding sizing, the power-to-energy ratio is equivalent to four hours of storage , while the battery capacity will be limited to 50% of the net nominal power of the associated renewable park .
This procedure had been anticipated during the Future Energy Summit (FES) Caribbean 2026 , when Ricardo Guerrero , Vice Minister of Electric Power, confirmed the work to incorporate storage into renewable facilities in operation.
Subsequently, during the XI Energy Week , held in October in Santo Domingo, Joel Santos Echavarría , Minister of Energy and Mines, confirmed to Energía Estratégica the preparation of the tender , within a portfolio of contracts that also included new generation.
With the approval of both processes, the country establishes two different contracting pathways , one to add solar and wind capacity with integrated batteries and another to incorporate storage into operating parks.