Argentina's Energy Secretariat approved, through Resolution 325/2026 , the general procedure of the Additional Reliability Reserve Service (SerCA) , which establishes the conditions of remuneration, technological participation, guarantees and contractual terms to incorporate new firm power into the electrical system.
However, a second regulatory step remains. According to sources close to Energía Estratégica , after the publication of the general procedure, another resolution will be issued containing the specific numerical parameters for the calls for bids.
These will determine the total target firm power by technology and may also stipulate a specific capacity by region.
According to information obtained by this media outlet, the incorporation of between 1850 and 2950 MW of new firm capacity with commercial authorization until 2032 is currently being evaluated, although the volumes and their technological distribution do not yet have official confirmation.
For now, the regulations establish 10-year contracts for storage and renewable hybrids and 15-year contracts for thermal power plants , with a reference remuneration of USD 9000 per MW-month, adjusted by technological factors that will be defined in each call.
The official intention remains: to create a tool that allows the incorporation of new capacity under a criterion of technological neutrality and to use it recurrently according to the needs of the system.
Thermal power plants, storage, hybrid projects, renewable solutions with batteries, hydroelectric infrastructure and other technologies capable of providing firm power could compete there, with commercial authorization after January 1, 2025.
However, for hybrid projects, only bids that include commercially operational renewable energy plants from October 1, 2026 onwards will be accepted.
“In addition, the renewable generation capacity cannot be less than the proposed storage capacity (...) For renewables, the capacity will be considered “associated with 90% firmness in the periods of highest demand”, specifies the Annex of Resolution 325/2026.
The Dispatch Authority (OED) will calculate capacity requirements based on the maximum forecasted demand and the available supply during those hours. For renewables, the power capacity considered will be that “associated with 90% firmness during peak demand periods.”
Regarding income, the monthly consideration will include the available power, the value offered and awarded, the technological, incentive and seasonality coefficients, and the deductions on marginal income.
“The SerCA Remuneration does not replace the remuneration for energy or power that corresponds to the generator for its performance in the MEM,” the regulations clarify.
The reference amount will be updated annually according to the United States Producer Price Index (PPI), once the first year has elapsed since the commercial authorization of the entire allocated capacity.
For generators whose monthly dispatch exceeds 70% of their availability, 50% of the marginal revenue from energy obtained in the Spot Market will be deducted. Below 30%, there will be no deductions, and a linear relationship will be applied between these two extremes.
“No discount will be applied to energy traded on the Term Market,” the regulations state.
So, what figures are being discussed within the Ministry of Energy? According to information obtained by Energía Estratégica, the design under analysis includes between 250 and 350 MW of four-hour stand-alone batteries , with one year to become operational, and between 400 and 600 MW of renewable hybrids with six hours of storage, with two years to complete.
For open cycle thermal plants and modernizations, between 600 and 1000 MW are being considered, with a three-year timeframe, while the new combined cycle plants would contribute another 600 to 1000 MW, with a five-year timeframe.
Regarding technological factors, the evaluation considers applying 60% for independent storage (USD 5400 per MW-month), 100% for hybrids (USD 9000), 150% for gas turbines and engines (USD 13500) and 200% for combined cycles (USD 18000).
It should be clarified that none of these parameters were officially confirmed and the amounts do not necessarily represent the final consideration.
One of the models that is gaining strength combines public tenders with a dynamic similar to that of the Renewable Energy Term Market (MATER), which has quarterly calls to assign dispatch priority according to the availability of transport.
The delay was not initially part of the sector's calculations. More than two months ago, Energy Secretary María Tettamanti had anticipated that the regulation could be released within the next 15 days and even predicted that "around 1000 MW per year will have to be incorporated."
The economic and contractual requirements to compete for the SerCA
Resolution 325/2026 establishes a 5% Offer Maintenance Guarantee , calculated on the product between the megawatts offered and the Reference Investment Value (RIV).
In addition, there are quarterly capacity reservation payments that the successful bidders must make until they become operational, differentiated by technology and increasing if they enter the extension period.
“Those projects that become commercially viable within the target reference period will recover 100% of the amount corresponding to the payments made as charges prior to the COD,” the document states.
The remaining funds will be allocated to the Export Account to finance energy infrastructure projects.
Each call for tenders will set a target date for commissioning per technology, with a maximum extension of two years , subject to system requirements.
“Partial commercial operation will be permitted provided it is not less than 50% of the assigned power,” the regulations stipulate. If this occurs before the reference deadline, the contract will not take effect.
Furthermore, delays will reduce the duration of the agreement by the same amount as the delay incurred. If, by the expiration of the maximum term, 100% of the allocated capacity is not operational, the contract will be terminated without the right to claim any previously paid fees.