Bolivia's National Electricity Company (ENDE) launched an international public tender to contract the construction of the Contorno Bajo I photovoltaic solar plant, of at least 40 MW , which will be developed in the municipality of Viacha, department of La Paz.
The call for tenders, published on November 16 under code ENDE-KFW-2026-002 , will accept proposals until December 28, 2026. The contract covers engineering, equipment supply, civil works, assembly, and commissioning of the complex, including its connection to the National Interconnected System (SIN).
The project has financial backing from the German government, through the development bank KfW . In June of this year, Bolivia enacted Law No. 1738, which approved a loan agreement for up to 34 million euros for its implementation.
According to official documentation, the installation will have a minimum nominal power of 40 MW in alternating current and will incorporate a 24.9/115 kV step-up substation, in addition to an interconnection line of approximately 800 meters to the existing Contorno Bajo substation.

The project also includes the adaptation of a 115 kV line bay, with the aim of allowing the injection of electricity into the national grid.
Requirements to compete for the EPC contract
The call establishes a single-stage selection process and provides for hiring under the FIDIC Yellow Book conditions, used in engineering and construction projects.
To participate, companies must demonstrate experience in five photovoltaic projects of at least 40 MW , in addition to three solar plants developed in South America that have been in operation for a minimum of two years.
In financial matters, ENDE requires a minimum average annual turnover of 60 million euros , calculated on the five best years since 2011, and proven access to financial resources of 40 million euros.
Continue reading
The official schedule estimates an execution period of 14 months , with a planned start in May 2027 and commissioning around June 2028.
According to information presented to the Chamber of Deputies, the project design includes 74,412 photovoltaic panels of 540 W , distributed over an area of 35.43 hectares, and an estimated useful life of 25 years.
The construction tender is complemented by another international process launched by ENDE to contract consulting services to supervise the execution, control the quality of the works, and support the commissioning. This second process will accept proposals until December 21, 2026 .
Bolivia adds renewable energy projects and seeks to attract private investment
The announcement comes amid a wave of new photovoltaic developments in Bolivia. In November, the Rural Electrification Cooperative (CRE) began construction of the 3.6 MWp Río Seco solar park in the department of Santa Cruz.
The initiative, awarded to Switch Green under a turnkey contract, is part of the cooperative's strategy to develop more than 120 MW of renewable energy generation . The Río Seco project is currently under construction and is expected to feed electricity into the national grid.
In parallel, the Bolivian government presented in May 2026 a draft of a new Electricity and Renewable Energy Law , aimed at expanding private participation in generation, transmission and distribution.
As reported by Energía Estratégica , the proposal aims to incorporate competitive contracting mechanisms, long-term contracts, and an independent regulatory entity, with the purpose of attracting investment and facilitating the development of new renewable energy plants.
In this context, the Contorno Bajo I tender represents a concrete opportunity for international contractors specializing in large-scale solar projects , as Bolivia moves forward with new investments in electrical infrastructure and diversification of its generation matrix.