The Federal Electricity Commission (CFE) is moving forward with the bidding process for the Oasis Hybrid Power Plant , a project that will integrate solar photovoltaic generation, batteries, and green hydrogen (H2V) in Baja California Sur, Mexico. In this context, HDF LATAM expressed its interest in the bidding process and submitted ten formal inquiries to clarify the economic, financial, contractual, and technical conditions of the initiative.
According to official CFE documents accessed by Energía Estratégica , the company's questions focus on aspects such as guarantees of USD 10,000 per MW offered, national content requirements, financial structuring, consortium formation, and environmental responsibilities .
The procedure, identified as COEE-0027-2026 , began its clarification session on November 11, 2026 , when CFE recorded the ten questions submitted by HDF LATAM through the Special Scheme Contracting System (SCOEE).
The session was suspended and its resumption was set for November 17 , according to the official minutes issued by the Engineering and Infrastructure Projects Directorate of the state-owned company.
HDF LATAM's interest was also documented during a technical visit on November 3 , in which representatives of the firm and Grupo Constructor Industrial (GCI) participated, along with personnel from different areas of CFE.
The Oasis Hybrid Power Plant includes 72 MW of direct current photovoltaics, equivalent to 60 MW of alternating current , in addition to a 20 MW and 80 MWh battery storage system, capable of delivering electricity for four hours.
The planned configuration also incorporates 20 MW for electrolysis to produce H2V and four 1.5 MW fuel cells, with a combined power of 6 MW to convert the stored hydrogen into electricity.
The complex will be geared towards supplying the Mulegé Isolated System , where the state-owned company seeks to increase the participation of renewable sources and reduce the consumption of fossil fuels through generation and storage technologies.
The 10 conditions that HDF LATAM seeks to clarify before CFE
One of the main aspects identified in the official documents corresponds to the economic guarantee of USD 10000 x MW offered , established in the Process Letter of the competition.
HDF LATAM requests confirmation of the capacity used to calculate this bond, considering that Oasis will integrate facilities with different nominal power ratings and functions within the electrical system.
In its presentation, the company indicates that the plant will not deliver more than 20 MW to the Mulegé System and asks whether the guarantee should be calculated on the Guaranteed Net Capacity at the point of interconnection, instead of considering the installed photovoltaic capacity or other components.
This definition is relevant to interested parties, since the calculation basis directly affects the amount of the guarantee required to participate in the procedure.
Another point raised involves the requirements of a minimum of 10% national content and 90% national content in labor , for which HDF LATAM requests that CFE specify the verification methodology.
The concerns also extend to the conditions for private participation. The company needs to confirm whether interested parties can demonstrate experience and technical and financial capacity through partners, engineering contractors, suppliers, or affiliated companies .
In particular, it raises the possibility of using background information from companies specializing in the construction and commissioning of high-voltage substations, even if these activities have not been carried out directly by the developer.
It also requests clarification on the formation of consortia with investors after the bidding process , an alternative that could affect the business and financial structuring of the proposals.
The revenue model is another central aspect of the exchange.
According to the questions officially submitted, HDF LATAM warns that the financial calculator planned for the competition contemplates differentiated income for solar generation and storage , while Oasis integrates photovoltaic energy, batteries and an H2V system within the same power plant.
For this reason, it requests that the target profitability, the offered rate, and the allocation of investments and income among the different technological components be evaluated.
The documentation also refers to a contractual provision by which CFE would acquire 100% of the products of the plant , although the interested company requests clarifications about its representation within the financial model.
Another concern relates to the contractual documents given to potential participants.
HDF LATAM identifies that one of the models bears the name CFE-Arcadia and includes references to wind turbines in provisions on operation and maintenance, even though Oasis corresponds to a photovoltaic installation with batteries and hydrogen.
Therefore, the company requests confirmation as to whether CFE will provide a specific contractual version for Oasis before the submission of bids and at what point the bidders' comments should be incorporated.
Continue reading
Water, permits and deadlines: other pending definitions
Official documentation also allows the identification of queries related to the water infrastructure needed to produce green hydrogen.
HDF LATAM requests that CFE determine who will assume the responsibilities related to the disposal of sludge and waste, the discharge of reject water and the obtaining of concessions and permits before the National Water Commission (CONAGUA) .
The application includes the definition of the operation and maintenance obligations of the Wastewater Treatment Plant (WWTP) associated with the project.
In addition, the company raises questions about the environmental and regulatory permits that will need to be obtained to develop the power plant.
The procedures mentioned include the Environmental Impact Statement, the change of land use, the generation permit before the National Energy Commission and the interconnection studies before the National Energy Control Center .
The document also includes a query on the degree of flexibility that will exist to negotiate the development guarantees established in the competition.
The hiring process included a preliminary stage of technical outreach to potential participants.
According to an official record dated November 3, 2026 , CFE organized a visit to the Oasis site, with the meeting point at the facilities of the Guerrero Negro II Internal Combustion Power Plant .
Representing HDF were Ana Sofía Esquivel , Project Manager, and Gilberto Paredes Trasviña , Project Assistant. Alejandro Hernández Hernández , Project Manager, attended on behalf of Grupo Constructor Industrial .
The event also included CFE personnel from the areas of generation, civil engineering, operation and maintenance, instrumentation and control, among other specialties.
During the meeting, the Generation Sub-Directorate presented the general characteristics of the project and subsequently accompanied the business representatives on a tour of the land called Santa Brígida .
The inspection included the access points to the site from the highway, the central area where the installation of the generation equipment is planned, and the locations related to water supply and treatment.
The attendees also toured the electrical interconnection point with the Guerrero Negro II Power Plant , located within the land where Oasis will be developed.
According to the minutes, once the inspection was completed, CFE consulted the company representatives about any possible doubts or comments, without any observations being made at that time.
The participation of HDF LATAM and Grupo Constructor Industrial in the technical visit does not constitute an award nor does it confirm that both companies have submitted economic proposals .
Oasis and Puerto Peñasco: CFE accelerates the contracting of renewable energy projects
The Oasis tender is part of a broader portfolio of projects promoted by CFE within its 2026-2030 Expansion Plan , which includes new generation plants, storage facilities and electrical infrastructure in Mexico.
In parallel, the state-owned company launched an international tender to contract the transmission grid reinforcement works associated with the Puerto Peñasco Photovoltaic Plant, Sequence III , in the states of Sonora and Baja California. As previously reported by Energía Estratégica , the COEE-0029-2026 tender has a maximum budget of 2,894.86 million Mexican pesos , excluding taxes, to carry out approximately 308.89 kilometers of 230 and 400 kilovolt electrical infrastructure .
The interventions include work on the Cucapah, Golfo de Santa Clara and Puerto Peñasco substations, as well as new transmission lines intended to support the expansion of the solar complex.
To participate, CFE requires contractors to have a minimum equity capital of 429.7 million Mexican pesos , experience in high-voltage infrastructure, and a minimum percentage of 90% national labor , among other technical and financial conditions.
The project is linked to the expansion of Puerto Peñasco, whose third phase will incorporate 300 MW of photovoltaic capacity and battery storage . The overall plan for the complex anticipates reaching 1,000 MW of solar power once its four phases are completed.
Meanwhile, in Baja California Sur, Oasis represents a different type of investment , integrating photovoltaic generation, batteries and H2V production to strengthen the supply of the Mulegé Isolated System.
Both procedures reflect CFE's progress in contracting renewable energy generation and electrical grid projects , although with specific scopes and requirements for interested companies.